Hi Parul,
What is the Issue you are facing during copy ?
Hope you have completed below key points:
1. Installed Analysis Office
2. Created Planning Category
3. Maintained user parameters "CAC" with controlling area
4. Updated Planned Values in IBP using analysis office
Once you have implemented Integrated Business Planning and above points completed, follow below steps to copy plan values:
Step1: Open Analysis Office
Step2: Go to File, Select Analysis - Select Open Work Book - Select System - Login - enter *SFIN* and enter - select following any of following work book names in prompt
/ERP/SFIN_A09_WB01 Cost Center Planning Integration SFIN – Classical
l /ERP/SFIN_A19_WB01 Internal Orders Planning Integration SFIN - Classical
l /ERP/SFIN_A29_WB01 Project Planning Integration SFIN - Classical
Step3 - Enter input variables, It will show ERP Values and IBP Values
Step 4 - You can choose option of copy plan values to ERP and click to copy
Please refer SAP help Working with Planning Workbooks - Integrated Business Planning for SAP Simple Finance Add-On for S - SAP Library
Please do let me know if you still require any further information.
Regards,
Santosh Varanasi